aallen

About Amy Allen

This author has not yet filled in any details.
So far Amy Allen has created 15 blog entries.

Farview Circle & Richlee Drive Water Main Replacement

OCWA’s installation phase of the new 8” water main along Farview Circle has been completed. We are moving into the testing and disinfection phase.  At this point we will pressure test, disinfect, then sample the new water main to ensure that it was correctly installed and disinfected. This process could take between 1-2 weeks depending [...]

2020-09-11T11:28:21-04:00September 11th, 2020|

Farview Circle Main Replacement Town of Camillus

OCWA has begun the first phase in the water main replacement along Farview Circle in Camillus. Construction activities associated with water main replacement projects are fluid, and ever changing as the work progresses. Our foremost concern is the safety of the residents and our working crews. As we advance in enhancing the water quality to [...]

2020-08-28T14:10:30-04:00August 28th, 2020|

Cleaning and Lining Lynnbrook Circle Update 08/11/2020

All temporary services have been removed on Lynnbrook Circle, Town of Onondaga.  Residents on that road are now back on the newly cleaned and lined water main.  Restoration and clean up will commence in the near future. On behalf of Mainlining America & OCWA we would like to thank everyone for their patience as we [...]

2020-08-11T11:40:22-04:00August 11th, 2020|

Cleveland Rd. Water Main Replacement Update (Construction Complete)

Major construction activities for the Cleveland Road project are now complete.  D.E. Tarolli, Inc. is now in the process of paving and will soon begin finishing lawn restoration.  There are a few remaining items that will be addressed in the next couple of weeks, such as removing any remaining blow offs, removing old hydrants, and [...]

2020-08-11T11:34:43-04:00August 11th, 2020|

East Molloy Road Water Main Replacement Update (Construction Complete)

Major construction activities for the Molloy Road project are complete as of July 15, 2020. D.E. Tarolli, Inc. is now in the process of paving and will soon begin finishing lawn restoration. There are a few remaining items that will be addressed in the next couple of weeks, such as removing any remaining blow offs, [...]

2020-07-15T09:12:04-04:00July 15th, 2020|

Cleveland Rd. Water Main Replacement Update

OCWA’s water main replacement project along Cleveland Road Town of Onondaga has proceeded to the service installation phase of construction. The new water main has been installed, pressure tested, disinfected, bacteriological samples taken/passed, and Health Dept. approval received. During this phase, construction activities will once again ramp up in the area.  Construction activities will be [...]

2020-07-15T09:11:03-04:00July 15th, 2020|

Lakeview Terrace Water Main Replacement Update (Construction Complete)

Major construction activities for the Lakeview Terrace project are complete as of July 16, 2020. D.E. Tarolli, Inc. is now in the process of paving and will soon begin finishing lawn restoration. There are a few remaining items that will be addressed in the next couple of weeks, such as removing any remaining blow offs, [...]

2020-07-15T09:09:23-04:00July 15th, 2020|

East Molloy Road Water Main Replacement Update

The following are the latest updates and projected timelines for completion of water main work along Molloy Road in the Town of Cicero: All new water main lines have been installed All new water main lines have been tested & chlorinated with all bacteriological samples passing. Onondaga County Health Dept approval has been received. All [...]

2020-06-26T15:59:33-04:00June 26th, 2020|

Lakeview Terrace Water Main Replacement Update

OCWA’s water main replacement project along Lakeview Terrace has proceeded to the "service" installation phase of construction. The new water main has been installed, pressure tested, disinfected, bacteriological samples taken & passed, and Health Dept. approval received.  Now individual homes (or services) will be connected to the new main. During this phase, construction activities will [...]

2020-06-26T15:55:19-04:00June 26th, 2020|

Cleaning and Lining Knowell Road & Richlee Drive Update 06/19/2020

All temporary services have been removed on Knowell Road. Residents on that road are now back on the newly cleaned and lined water main. Starting next week (week of 06/22/20) the temporary water system for Richlee Drive, from Knowell Road to Braeside Lane, will start being put in place. Residents along Richlee Drive can expect [...]

2020-06-19T08:54:51-04:00June 19th, 2020|