Our Fairmount location is undergoing some significant updates, including the construction of two new covered tanks. Below are several relevant updates for this project:
- The Contractor completed the new East Tank and it officially went into service on January 14, 2022.
- The East Tank was painted with an aesthetic coating in early August of 2022.
- In early December of 2022, the new West Tank’s roof was poured.
- The remaining tank and piping work was recently completed.
The next step is disinfection of the West Tank. The West Tank is expected to go into service in February 2023. There is additional sitework that will continue as the weather permits. Any remaining work will be finished by the late spring or early summer of 2023.
New East Tank in Operation – 6 Million Gallons
Fairmount Prior to roof Completion of the West Tank
Inside the West Tank
New West Tank Nearing Completion – 6 Million Gallons