OCWA’s water main replacement project along Lakeview Terrace has proceeded to the “service” installation phase of construction. The new water main has been installed, pressure tested, disinfected, bacteriological samples taken & passed, and Health Dept. approval received. Now individual homes (or services) will be connected to the new main.
During this phase, construction activities will once again ramp up in the area. Construction activities will be fluid as we move from house to house, switching over services. The need for one-way flagging operations, lane/shoulder closures, and brief detours may be required.
We have begun switching over each residence’s water service from the old water main to the newly installed water main. During this process you will notice a brief interruption of your water service (10-20 minutes).
Both D.E. Tarolli and OCWA would like to thank area residents for their patience during the construction phase. Please direct any questions to sjdrake@ocwa.org.