2006 Consumer Confidence Report & Annual Water Supply Statement
Important information about your water supply
May 2007
The Onondaga County Water Authority is once again pleased to provide its
customers and consumers with the Authority's 2006 Annual Water Supply Statement
and Consumer Confidence Report. Throughout this report readers will be able to
find useful information specifically related to OCWA as well as information
related to water in general. In addition to mailing the report to all
customers of record, the Authority continues its practice of providing copies
of the report to local libraries and posting the text on the Internet.
The Authority had a very busy year in 2006 with respect to capital projects and
system growth.
During the year, projects completed included the following:
-
Substantial completion of a 1-MG elevated Central Square tank replacement
-
Completion of the Oneida River crossing for a new 16-inch feed to southern Oswego
-
Construction of the Caughdenoy Pumping Station
-
Improvements to the distribution maintenance facility in Oswego
-
Completion of a year-long pilot plant study related to future improvements to the Marcellus Water Treatment Plant.
-
OCWA added 64,452 feet of new water main and replaced an additional 29,670 feet of main.
-
The Authority also replaced 121 hydrants and added 154 new hydrants.
Two other key highlights include addition of the Village of East Syracuse water
system as full-time wholesale customer and the lease of the Village of Minoa
water system, converting 1150 customers from wholesale to retail.
Looking ahead into 2007, OCWA will continue its ongoing improvement efforts.
With the water treatment plant study in hand, the Authority has begun design of
the recommended improvements. In addition to planned main and hydrant
replacements, OCWA also has two replacement storage tank projects underway,
with a 1-MG tank being constructed in Van Buren that will replace tanks located
in Lakeland and Geddes and 1.5-MG tank being constructed in Canastota.
Additionally, OCWA is working in a cooperative effort with the Metropolitan
Water Board and Onondaga County leadership to meet the Federal mandate related
to the construction of finished water storage facilities for the County. In
the coming days and months, all of us will be hearing and learning more about
this essential project.
To learn more about the OCWA water system and water supply, you are urged to
read the information included in this report and to visit the Authority web
site, www.ocwa.org. The Authority remains interested in your comments and
suggestions related to this report and how we can make this report more useful.
To assist us with collecting your comments, a special extension has been set
up that can be contacted 24 hours a day between now and June 30, 2007. Readers
of this report can call 315-455-7061 x3116 to record their remarks.
|
Robert F. Tomeny
|
Michael E. Hooker
|
Anthony J. Geiss, Jr, PE
|
|
Chairman, OCWA Board
|
Executive Director
|
Deputy Executive Director
|
More information: or 315-455-7061